2010 Publication Schedule: Difference between revisions

From IHE Wiki
Jump to navigation Jump to search
Witting (talk | contribs)
Witting (talk | contribs)
Line 15: Line 15:
* 2010-06-11 Due  
* 2010-06-11 Due  
<u>Integration of approved CPs into TI and TF documents</u><br>
<u>Integration of approved CPs into TI and TF documents</u><br>
* 2010-06-tbd Begin
* 2010-06-17 Begin
* 2010-07-tbd Completion for all TI being moved to FT  
* 2010-06-24 Completion for all TI being moved to FT  
* 2010-07-tbd Completion for all TI and TF, including integrating TI becoming FT into the TF  
* 2010-07-01 Completion for all TI and TF, including integrating TI becoming FT into the TF  
<u>Review by committee</u><br>
<u>Review by committee</u><br>
* 2010-07-tbd Begin  
* 2010-07-05 Begin  
* 2010-07-tbd Due  
* 2010-07-16 Due  
<u>Integration and resolution of commitee comments</u><br>
<u>Integration and resolution of commitee comments</u><br>
* 2010-07-tbd Begin  
* 2010-07-19 Begin  
* 2010-07-26 Complete
* 2010-07-26 Complete
=== Assignment of editors===
* XCA/XCPD/XDR/Async - Karen
* PIX/PDQ V3, DSUB - Vassil
* NAV - Rob
* RFD - George
* Vol. 1 - George
* Vol. 2a - John
* Vol. 2b - Manuel
* Vol. 2x - John
* Vol. 3 - Manuel
=== Moving to Final Text ===
* XDR - all conditions satisfied
* PIX/PDQ V3 - waiting for CP completion and assess on June 16


=== Helpful Hints for integration tasks ===
=== Helpful Hints for integration tasks ===
* See [[2009_Publication_Schedule#Helpful_Hints_for_integration_tasks | Helpful Hints]] for Integrating new Final Text profiles into Vol. 1 & 2
* See [[2009_Publication_Schedule#Helpful_Hints_for_integration_tasks | Helpful Hints]] for Integrating new Final Text profiles into Vol. 1 & 2

Revision as of 15:43, 27 April 2010

2010 Schedule of Publication


For a graphic view of this schedule see ITI 2010 Timeline.

Completion of all Public Comment Supplements

  • 2010-05-10 Deliver to sponsors for publication
  • 2010-05-24 Official publication by sponsors, start of public comment period
  • 2010-06-24 Public Comment Period Ends

Completion of new Trial Implementation Supplements, updated Trial Implementation Supplements and updated Technical Framework

  • 2010-07-26 Deliver to sponsors for publication
  • 2010-08-09 Official publication by sponsors

Last CP ballot for CPs being integrated into 2010 document

  • 2010-05-14 Released
  • 2010-06-11 Due

Integration of approved CPs into TI and TF documents

  • 2010-06-17 Begin
  • 2010-06-24 Completion for all TI being moved to FT
  • 2010-07-01 Completion for all TI and TF, including integrating TI becoming FT into the TF

Review by committee

  • 2010-07-05 Begin
  • 2010-07-16 Due

Integration and resolution of commitee comments

  • 2010-07-19 Begin
  • 2010-07-26 Complete

Assignment of editors

  • XCA/XCPD/XDR/Async - Karen
  • PIX/PDQ V3, DSUB - Vassil
  • NAV - Rob
  • RFD - George
  • Vol. 1 - George
  • Vol. 2a - John
  • Vol. 2b - Manuel
  • Vol. 2x - John
  • Vol. 3 - Manuel

Moving to Final Text

  • XDR - all conditions satisfied
  • PIX/PDQ V3 - waiting for CP completion and assess on June 16

Helpful Hints for integration tasks

  • See Helpful Hints for Integrating new Final Text profiles into Vol. 1 & 2