:* Publish CP Ballot in early-Jan 2013 (for CPs needed for IHE-Europe Connectathon in April 2013) | |||
:* Publish CP Ballot at end-of-April 2013 | :* Publish CP Ballot at end-of-April 2013 | ||
:* Incorporate FT CPs into updated TF released July 2013 | :* Incorporate FT CPs into updated TF released July 2013 | ||
| Line 11: | Line 12: | ||
:* 0? '''Completed''' CPs that failed ballot and need to be reworked | :* 0? '''Completed''' CPs that failed ballot and need to be reworked | ||
:* 5 '''Submitted''' CPs to review/assign | :* 5 '''Submitted''' CPs to review/assign (as of Oct 26 when this was due) | ||
::* 237 Incorrect reference in Rad 43 | ::* 237 Incorrect reference in Rad 43 | ||
::* 238 Align PDF & Text option names for XDS-I.b and XDR-I | ::* 238 Align PDF & Text option names for XDS-I.b and XDR-I | ||
| Line 20: | Line 21: | ||
List of "non-trivial" CPs: | List of "non-trivial" CPs: | ||
:* CP-xxx : Title (Author) | :* CP-xxx : Title (Author) | ||
:** | :** no "non-trivial" CPs were raised | ||
List of outstanding items not yet submitted as CPs: | List of outstanding items not yet submitted as CPs: | ||
:* | :* 3 more CPs were submitted between Oct 26 and Nov 1 | ||
List of other maintenance tasks: | List of other maintenance tasks: | ||
| Line 38: | Line 39: | ||
Effort Evaluation (as a % of Tech Cmte Bandwidth): | Effort Evaluation (as a % of Tech Cmte Bandwidth): | ||
:* | :* 15% total for maintenance with new templates only for new supplements | ||
Responses to Issues: | Responses to Issues: | ||
Latest revision as of 13:40, 1 November 2012
Target:
- Publish CP Ballot in early-Jan 2013 (for CPs needed for IHE-Europe Connectathon in April 2013)
- Publish CP Ballot at end-of-April 2013
- Incorporate FT CPs into updated TF released July 2013
Number of outstanding CPs:
- 30 Assigned CPs to work on
- For specifics refer to Tracking Doc and sort by Status
- (about 2/3 are stagnant) Should do a review/triage of dormant CPs and cancel or re-start
- 0? Completed CPs that failed ballot and need to be reworked
- 5 Submitted CPs to review/assign (as of Oct 26 when this was due)
- 237 Incorrect reference in Rad 43
- 238 Align PDF & Text option names for XDS-I.b and XDR-I
- 239 Refactor RAD-01 and RAD-12 Transactions with IHE ITI PAM
- 240 Clarify New Series Instance UID semantics in IOCM
- 241 Clarify how to handle retention policy expiry with XDS-I manifest deletion
List of "non-trivial" CPs:
- CP-xxx : Title (Author)
- no "non-trivial" CPs were raised
- CP-xxx : Title (Author)
List of outstanding items not yet submitted as CPs:
- 3 more CPs were submitted between Oct 26 and Nov 1
List of other maintenance tasks:
- Cleanup of Cross-Referencing to ITI (they renumbered their sections)
- Adoption of new IHE Templates <add link>
- Add 2 FT Supplements to TF (and any made FT next year)
- R2/RE Harmonization?
7. Risks
- Risk of effort spent on updating existing Supplements and TF to match new templates being low return-on-investment.
9. Tech Cmte Evaluation
Effort Evaluation (as a % of Tech Cmte Bandwidth):
- 15% total for maintenance with new templates only for new supplements
Responses to Issues:
- See italics in Risk and Open Issue sections
Candidate Editor:
- Kevin O'Donnell