Line 27: Line 27:
=== Assignment of editors===
=== Assignment of editors===
* XCA/XCPD/XDR/Async - Karen
* XCA/XCPD/XDR/Async - Karen
* PIX/PDQ V3, DSUB - Vassil
* PIX/PDQ V3, DSUB - Vassil : July 13 transfered to Manuel
* NAV - Rob
* NAV - Rob
* RFD - George
* RFD - George
Line 37: Line 37:


Assigned on July 12
Assigned on July 12
* PDO, SVS - Manuel
* PDO, SVS, MPQ - Manuel


=== Moving to Final Text ===
=== Moving to Final Text ===
* XDR - all conditions satisfied
* XDR - all conditions satisfied
* PIX/PDQ V3 - waiting for CP completion and assess on June 16
* PIX/PDQ V3 - at June 16 call agreed that CPs have not progressed so cannot move this to Final Text.  Will be released as Trial Implementation another year with hopes that CP progress is made in 2011.


=== Helpful Hints for integration tasks ===
=== Helpful Hints for integration tasks ===
* See [[2009_Publication_Schedule#Helpful_Hints_for_integration_tasks | Helpful Hints]] for Integrating new Final Text profiles into Vol. 1 & 2
* See [[2009_Publication_Schedule#Helpful_Hints_for_integration_tasks | Helpful Hints]] for Integrating new Final Text profiles into Vol. 1 & 2

Latest revision as of 16:20, 13 July 2010

2010 Schedule of Publication


For a graphic view of this schedule see ITI 2010 Timeline.

Completion of all Public Comment Supplements

  • 2010-05-10 Deliver to sponsors for publication
  • 2010-05-24 Official publication by sponsors, start of public comment period
  • 2010-06-24 Public Comment Period Ends

Completion of new Trial Implementation Supplements, updated Trial Implementation Supplements and updated Technical Framework

  • 2010-07-26 Deliver to sponsors for publication
  • 2010-08-09 Official publication by sponsors

Last CP ballot for CPs being integrated into 2010 document

  • 2010-05-14 Released
  • 2010-06-11 Due

Integration of approved CPs into TI and TF documents

  • 2010-06-17 Begin
  • 2010-06-24 Completion for all TI being moved to FT
  • 2010-07-01 Completion for all TI and TF, including integrating TI becoming FT into the TF

Review by committee

  • 2010-07-05 Begin
  • 2010-07-16 Due

Integration and resolution of commitee comments

  • 2010-07-19 Begin
  • 2010-07-26 Complete

Assignment of editors

  • XCA/XCPD/XDR/Async - Karen
  • PIX/PDQ V3, DSUB - Vassil : July 13 transfered to Manuel
  • NAV - Rob
  • RFD - George
  • Vol. 1 - George
  • Vol. 2a - John
  • Vol. 2b - Manuel
  • Vol. 2x - John
  • Vol. 3 - Manuel

Assigned on July 12

  • PDO, SVS, MPQ - Manuel

Moving to Final Text

  • XDR - all conditions satisfied
  • PIX/PDQ V3 - at June 16 call agreed that CPs have not progressed so cannot move this to Final Text. Will be released as Trial Implementation another year with hopes that CP progress is made in 2011.

Helpful Hints for integration tasks