2010 Publication Schedule: Difference between revisions
Jump to navigation
Jump to search
New page: === 2010 Schedule of Publication=== <br> For a graphic view of this schedule see [ftp://ftp.ihe.net/IT_Infrastructure/iheitiyr8-2010-2011/Technical_Cmte/2010.ITITimeline.ppt ITI 2010 Time... |
|||
| (6 intermediate revisions by the same user not shown) | |||
| Line 12: | Line 12: | ||
* 2010-08-09 Official publication by sponsors | * 2010-08-09 Official publication by sponsors | ||
<u>Last CP ballot for CPs being integrated into 2010 document</u><br> | <u>Last CP ballot for CPs being integrated into 2010 document</u><br> | ||
* | * 2010-05-14 Released | ||
* | * 2010-06-11 Due | ||
<u>Integration of approved CPs into TI and TF documents</u><br> | <u>Integration of approved CPs into TI and TF documents</u><br> | ||
* | * 2010-06-17 Begin | ||
* | * 2010-06-24 Completion for all TI being moved to FT | ||
* | * 2010-07-01 Completion for all TI and TF, including integrating TI becoming FT into the TF | ||
<u>Review by committee</u><br> | <u>Review by committee</u><br> | ||
* | * 2010-07-05 Begin | ||
* | * 2010-07-16 Due | ||
<u>Integration and resolution of commitee comments</u><br> | <u>Integration and resolution of commitee comments</u><br> | ||
* | * 2010-07-19 Begin | ||
* | * 2010-07-26 Complete | ||
=== Assignment of editors=== | |||
* XCA/XCPD/XDR/Async - Karen | |||
* PIX/PDQ V3, DSUB - Vassil : July 13 transfered to Manuel | |||
* NAV - Rob | |||
* RFD - George | |||
* Vol. 1 - George | |||
* Vol. 2a - John | |||
* Vol. 2b - Manuel | |||
* Vol. 2x - John | |||
* Vol. 3 - Manuel | |||
Assigned on July 12 | |||
* PDO, SVS, MPQ - Manuel | |||
=== Moving to Final Text === | |||
* XDR - all conditions satisfied | |||
* PIX/PDQ V3 - at June 16 call agreed that CPs have not progressed so cannot move this to Final Text. Will be released as Trial Implementation another year with hopes that CP progress is made in 2011. | |||
=== Helpful Hints for integration tasks === | === Helpful Hints for integration tasks === | ||
* See [[2009_Publication_Schedule#Helpful_Hints_for_integration_tasks | Helpful Hints]] for Integrating new Final Text profiles into Vol. 1 & 2 | * See [[2009_Publication_Schedule#Helpful_Hints_for_integration_tasks | Helpful Hints]] for Integrating new Final Text profiles into Vol. 1 & 2 | ||
Latest revision as of 16:20, 13 July 2010
2010 Schedule of Publication
For a graphic view of this schedule see
ITI 2010 Timeline.
Completion of all Public Comment Supplements
- 2010-05-10 Deliver to sponsors for publication
- 2010-05-24 Official publication by sponsors, start of public comment period
- 2010-06-24 Public Comment Period Ends
Completion of new Trial Implementation Supplements, updated Trial Implementation Supplements and updated Technical Framework
- 2010-07-26 Deliver to sponsors for publication
- 2010-08-09 Official publication by sponsors
Last CP ballot for CPs being integrated into 2010 document
- 2010-05-14 Released
- 2010-06-11 Due
Integration of approved CPs into TI and TF documents
- 2010-06-17 Begin
- 2010-06-24 Completion for all TI being moved to FT
- 2010-07-01 Completion for all TI and TF, including integrating TI becoming FT into the TF
Review by committee
- 2010-07-05 Begin
- 2010-07-16 Due
Integration and resolution of commitee comments
- 2010-07-19 Begin
- 2010-07-26 Complete
Assignment of editors
- XCA/XCPD/XDR/Async - Karen
- PIX/PDQ V3, DSUB - Vassil : July 13 transfered to Manuel
- NAV - Rob
- RFD - George
- Vol. 1 - George
- Vol. 2a - John
- Vol. 2b - Manuel
- Vol. 2x - John
- Vol. 3 - Manuel
Assigned on July 12
- PDO, SVS, MPQ - Manuel
Moving to Final Text
- XDR - all conditions satisfied
- PIX/PDQ V3 - at June 16 call agreed that CPs have not progressed so cannot move this to Final Text. Will be released as Trial Implementation another year with hopes that CP progress is made in 2011.
Helpful Hints for integration tasks
- See Helpful Hints for Integrating new Final Text profiles into Vol. 1 & 2