Created page with "==Attendees== ==Minutes== *Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European C..."
 
 
(13 intermediate revisions by the same user not shown)
Line 1: Line 1:
==Attendees==
==Attendees==
 
*Wim Corbijn (Philips)
 
*Kinson Ho (Agfa)
*Jon Zammit (CCO)
*Charles Smith
*Kevin O'Donnell (Toshiba)
*Mike Bohl (Radiology Group)
*Steve Massey
*Lynn Felhofer (Project Manager)
*Yasunari Shiokawa (IHE-J)
*Antje Schroeder (Siemens)
*David Clunie (PixelMed)
*Teri Sippel Schmidt (Karos)
*Elliot Silver (McKesson)
*Nichole Drye-Mayo (RSNA)


==Minutes==
==Minutes==
 
*[https://docs.google.com/spreadsheets/d/1TmSwnn4AIiXqFLc_AtzP0dNd9LUWnA-ZcCjBMKpLzp4/edit?usp=sharing IHE RAD CP Tracking Document]
*Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European Connectathon.
*Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European Connectathon.
**CP-RAD-337 Assigned to David Clunie.
**CP-RAD-338 Completed.  Will need to highlight during ballot so objections can be raised if there is evidence of invalidating implementations.  May need a communication task leading up to Connectathon so implementers are not blindsided that for Image Displays there IS a difference between the requirements for SWF conformance and SWF.b conformance. Put out in next ballot round.
**CP-RAD-339 Assigned to David Clunie.
**CP-RAD-340 Completed.  Will put in Ballot.
**CP-RAD-341 Assigned to Elliot Silver.
**CP-RAD-342 Assigned to Kinson Ho. Kinson will check if there are mandatory behaviors. Review at next meeting.
**CP-RAD-343 Assigned to Lynn Felhofer. More content text needed.
**CP-RAD-344 Assigned to Kinson Ho. 
**CP-RAD-345 Assigned to Elliot Silver.  Will replace with generic email for either IHE Canadd or IHE Radiology. 
**CP-RAD-346 Assigned to Teri Sippel Schmidt and Lynn Felhofer.
**CP-RAD-347 Assigned to Elliot Silver.
***Top 11 CPs:  281, 293, 307, 209, 312, 313, 314, 328, 339, 342, 346
***Kinson, Teri, Kevin and Lynn will have CPs ready by 11/30 (1 week before RSNA 2015)

Latest revision as of 10:39, 19 October 2015

Attendees

  • Wim Corbijn (Philips)
  • Kinson Ho (Agfa)
  • Jon Zammit (CCO)
  • Charles Smith
  • Kevin O'Donnell (Toshiba)
  • Mike Bohl (Radiology Group)
  • Steve Massey
  • Lynn Felhofer (Project Manager)
  • Yasunari Shiokawa (IHE-J)
  • Antje Schroeder (Siemens)
  • David Clunie (PixelMed)
  • Teri Sippel Schmidt (Karos)
  • Elliot Silver (McKesson)
  • Nichole Drye-Mayo (RSNA)

Minutes

  • IHE RAD CP Tracking Document
  • Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European Connectathon.
    • CP-RAD-337 Assigned to David Clunie.
    • CP-RAD-338 Completed. Will need to highlight during ballot so objections can be raised if there is evidence of invalidating implementations. May need a communication task leading up to Connectathon so implementers are not blindsided that for Image Displays there IS a difference between the requirements for SWF conformance and SWF.b conformance. Put out in next ballot round.
    • CP-RAD-339 Assigned to David Clunie.
    • CP-RAD-340 Completed. Will put in Ballot.
    • CP-RAD-341 Assigned to Elliot Silver.
    • CP-RAD-342 Assigned to Kinson Ho. Kinson will check if there are mandatory behaviors. Review at next meeting.
    • CP-RAD-343 Assigned to Lynn Felhofer. More content text needed.
    • CP-RAD-344 Assigned to Kinson Ho.
    • CP-RAD-345 Assigned to Elliot Silver. Will replace with generic email for either IHE Canadd or IHE Radiology.
    • CP-RAD-346 Assigned to Teri Sippel Schmidt and Lynn Felhofer.
    • CP-RAD-347 Assigned to Elliot Silver.
      • Top 11 CPs: 281, 293, 307, 209, 312, 313, 314, 328, 339, 342, 346
      • Kinson, Teri, Kevin and Lynn will have CPs ready by 11/30 (1 week before RSNA 2015)