==Attendees== | ==Attendees== | ||
*Wim Corbijn (Philips) | |||
*Kinson Ho (Agfa) | |||
*Jon Zammit (CCO) | |||
*Charles Smith | |||
*Kevin O'Donnell (Toshiba) | |||
*Mike Bohl (Radiology Group) | |||
*Steve Massey | |||
*Lynn Felhofer (Project Manager) | |||
*Yasunari Shiokawa (IHE-J) | |||
*Antje Schroeder (Siemens) | |||
*David Clunie (PixelMed) | |||
*Teri Sippel Schmidt (Karos) | |||
*Elliot Silver (McKesson) | |||
*Nichole Drye-Mayo (RSNA) | |||
==Minutes== | ==Minutes== | ||
*[https://docs.google.com/spreadsheets/d/1TmSwnn4AIiXqFLc_AtzP0dNd9LUWnA-ZcCjBMKpLzp4/edit?usp=sharing IHE RAD CP Tracking Document] | |||
*Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European Connectathon. | *Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European Connectathon. | ||
**CP-RAD-337 Assigned to David Clunie. | |||
**CP-RAD-338 Completed. Will need to highlight during ballot so objections can be raised if there is evidence of invalidating implementations. May need a communication task leading up to Connectathon so implementers are not blindsided that for Image Displays there IS a difference between the requirements for SWF conformance and SWF.b conformance. Put out in next ballot round. | |||
**CP-RAD-339 Assigned to David Clunie. | |||
**CP-RAD-340 Completed. Will put in Ballot. | |||
**CP-RAD-341 Assigned to Elliot Silver. | |||
**CP-RAD-342 Assigned to Kinson Ho. Kinson will check if there are mandatory behaviors. Review at next meeting. | |||
**CP-RAD-343 Assigned to Lynn Felhofer. More content text needed. | |||
**CP-RAD-344 Assigned to Kinson Ho. | |||
**CP-RAD-345 Assigned to Elliot Silver. Will replace with generic email for either IHE Canadd or IHE Radiology. | |||
**CP-RAD-346 Assigned to Teri Sippel Schmidt and Lynn Felhofer. | |||
**CP-RAD-347 Assigned to Elliot Silver. | |||
***Top 11 CPs: 281, 293, 307, 209, 312, 313, 314, 328, 339, 342, 346 | |||
***Kinson, Teri, Kevin and Lynn will have CPs ready by 11/30 (1 week before RSNA 2015) | |||
Latest revision as of 10:39, 19 October 2015
Attendees
- Wim Corbijn (Philips)
- Kinson Ho (Agfa)
- Jon Zammit (CCO)
- Charles Smith
- Kevin O'Donnell (Toshiba)
- Mike Bohl (Radiology Group)
- Steve Massey
- Lynn Felhofer (Project Manager)
- Yasunari Shiokawa (IHE-J)
- Antje Schroeder (Siemens)
- David Clunie (PixelMed)
- Teri Sippel Schmidt (Karos)
- Elliot Silver (McKesson)
- Nichole Drye-Mayo (RSNA)
Minutes
- IHE RAD CP Tracking Document
- Review submitted CPs, prioritize them and identify which ones need to be completed for ballot in January so they can be ready for the European Connectathon.
- CP-RAD-337 Assigned to David Clunie.
- CP-RAD-338 Completed. Will need to highlight during ballot so objections can be raised if there is evidence of invalidating implementations. May need a communication task leading up to Connectathon so implementers are not blindsided that for Image Displays there IS a difference between the requirements for SWF conformance and SWF.b conformance. Put out in next ballot round.
- CP-RAD-339 Assigned to David Clunie.
- CP-RAD-340 Completed. Will put in Ballot.
- CP-RAD-341 Assigned to Elliot Silver.
- CP-RAD-342 Assigned to Kinson Ho. Kinson will check if there are mandatory behaviors. Review at next meeting.
- CP-RAD-343 Assigned to Lynn Felhofer. More content text needed.
- CP-RAD-344 Assigned to Kinson Ho.
- CP-RAD-345 Assigned to Elliot Silver. Will replace with generic email for either IHE Canadd or IHE Radiology.
- CP-RAD-346 Assigned to Teri Sippel Schmidt and Lynn Felhofer.
- CP-RAD-347 Assigned to Elliot Silver.
- Top 11 CPs: 281, 293, 307, 209, 312, 313, 314, 328, 339, 342, 346
- Kinson, Teri, Kevin and Lynn will have CPs ready by 11/30 (1 week before RSNA 2015)