2010 Publication Schedule
2010 Schedule of Publication
For a graphic view of this schedule see
ITI 2010 Timeline.
Completion of all Public Comment Supplements
- 2010-05-10 Deliver to sponsors for publication
- 2010-05-24 Official publication by sponsors, start of public comment period
- 2010-06-24 Public Comment Period Ends
Completion of new Trial Implementation Supplements, updated Trial Implementation Supplements and updated Technical Framework
- 2010-07-26 Deliver to sponsors for publication
- 2010-08-09 Official publication by sponsors
Last CP ballot for CPs being integrated into 2010 document
- 2010-05-14 Released
- 2010-06-11 Due
Integration of approved CPs into TI and TF documents
- 2010-06-tbd Begin
- 2010-07-tbd Completion for all TI being moved to FT
- 2010-07-tbd Completion for all TI and TF, including integrating TI becoming FT into the TF
Review by committee
- 2010-07-tbd Begin
- 2010-07-tbd Due
Integration and resolution of commitee comments
- 2010-07-tbd Begin
- 2010-07-26 Complete
Helpful Hints for integration tasks
- See Helpful Hints for Integrating new Final Text profiles into Vol. 1 & 2