Difference between revisions of "PCD Planning Committee Action Items"

From IHE Wiki
Jump to navigation Jump to search
(→‎Action Items 130-139: complete entries in Action Items from that portion of July 27 meeting)
(→‎Action Items 100-109: minor update jjg)
Line 93: Line 93:
 
| '''<Owner>:'''  |  
 
| '''<Owner>:'''  |  
 
| '''<Participants>''' | John Garguilo
 
| '''<Participants>''' | John Garguilo
| '''<Due Date>'''  | August 31, 2011  
+
| '''<Due Date>'''  | November 30, 2011  
 
| '''<Status>''' |OPEN
 
| '''<Status>''' |OPEN
 
| '''<Comments>:'''  |  
 
| '''<Comments>:'''  |  
Initiated F2F May 3, 2010: Erin raised the issue of workflow – e.g., infusion pump messaging takes too long, hospitals complain. Christian observed that clinicians need an indication when data is not reliable for the purpose (e.g., latency, other). John Rhoads indicated that applications need to specify their own behavior. John Garguilo suggested that the implementation guide needs to address these issues. May 26, 2010: John Garguilo will participate, noting this is a broad issue that applies to all domains. Steve noted that this should be addressed by individual profiles and both the PC and TC. Steve asked if a template exists and Todd believes they have this as a Wiki page. This will be a PC item initially. John Garguilo will discuss with others at NIST to gain insight. June 9, 2010: John Garguilo indicated discussions will start soon. Sept. 1, 2010: John Garguilo reminded the PC of the need for this guide and its relation to user and vendor work. He will provide a short presentation at the F2F. Add to Monday F2F agenda. Change date to November 1. Dec. 1, 2010: John Garguilo is looking at other approaches within NIST for potential applicability. Change date to March 2. April 13, 2011: John Garguilo said NIST is looking at this and it will have a section on PCD. It will address issues not found in the TF, but important for developers. Change date to June 1. June 8, 2011: Change date to July 13. ''' July 20, 2011: Change date to August 31. '''
+
Initiated F2F May 3, 2010: Erin raised the issue of workflow – e.g., infusion pump messaging takes too long, hospitals complain. Christian observed that clinicians need an indication when data is not reliable for the purpose (e.g., latency, other). John Rhoads indicated that applications need to specify their own behavior. John Garguilo suggested that the implementation guide needs to address these issues. May 26, 2010: John Garguilo will participate, noting this is a broad issue that applies to all domains. Steve noted that this should be addressed by individual profiles and both the PC and TC. Steve asked if a template exists and Todd believes they have this as a Wiki page. This will be a PC item initially. John Garguilo will discuss with others at NIST to gain insight. June 9, 2010: John Garguilo indicated discussions will start soon. Sept. 1, 2010: John Garguilo reminded the PC of the need for this guide and its relation to user and vendor work. He will provide a short presentation at the F2F. Add to Monday F2F agenda. Change date to November 1. Dec. 1, 2010: John Garguilo is looking at other approaches within NIST for potential applicability. Change date to March 2. April 13, 2011: John Garguilo said NIST is looking at this and it will have a section on PCD. It will address issues not found in the TF, but important for developers. Change date to June 1. June 8, 2011: Change date to July 13. ''' July 20, 2011: Change date to August 31: change date to November 30. '''
  
  

Revision as of 10:49, 7 September 2011

To see changes between current and last(or any earlier) versions of the action item list, click the history tab at the top of the page, select versions to compare and click compare command.

Significant recent changes, other than dates, will be in bold.

Decision meetings will have minutes that require approval. This may be accomplished by email ballot.

See also PCD Planning Committee Closed Action Items page.


Action Items 40-89

No. Action Item Owner Participants Due Open/Closed Description/Update
71 Recruit clinicians; develop novel ways, attend to their priorities and schedules Ken, Manny -- September 7, 2011 Open Profile development may be a reasonable initial focus for involvement and perhaps lead to further involvement in PCD. Paul had suggested a booth at at ACC, other meetings. Liase with standards groups such as ASTM, professional societies. Manny spoke with Christel Anderson, HIMSS. Steve is talking with the Mass Health Data Consortium. Nov. 4: Todd will talk with Chris Dinegar about the AAMI program, and is preparing a Tcon for ACCE. Dec. 2, 2009: Manny and Todd did a presentation for ACCE, will get in touch with Chris Dinegar. June 23: Recruiting at AAMI. July 21, 2010: Several companies have recently expressed an interest in participating in PCD: Stryker, Nuvon, expressed interest in becoming more active. D. Leyva (Nuvon) is co-chair of CCHIT committee for ambulatory health care and author of HITECH Survival Guide (survivalguide.com). Sept. 1, 2010: The first day of the F2F will include introduction/orientation as was done in Berkeley. John Leung mentioned a biomed conference in Canada and would like to explore a mini-showcase. Sept. 29, 2010: F2F includes an orientation for local people; invitations have been sent and others will follow. John Leung is working on a mini-showcase in Toronto. Jan. 12, 2011: Ken noted that there will be IHE recruiting sessions at HIMSS. Ken will respond to the invitation. Manny draft press release. Feb. 2, 2011: Steve will ask John Leung for an update. April 13, 2011: Steve received no response. Spring 2011 F2F: Recruiting clinician participation in PCD:
o Christel will schedule a PCD presentation for one of her monthly meetings with clinical informatics professionals. Erin and Ioana will conduct the presentation. Ken will add some “to do” items.
o Christel can help arrange for PCD interaction with nursing informatics professionals through ANI which has 20 some odd member organizations.

June 22, 2011: Erin indicated that the Webex will take place in August. July 20, 2011: Ken will post his slide set which may have some useful slides.

72 Press releases as recruiting tool, including the Showcase. Modify to include marketing IHE, PCD Manny -- Open Open Manny to ask Tom, Nick for information to use re IDCO Trial Implementation version. October 21, 2009: Erin offered to solicit publications. Steve suggested a Wiki page for this purpose. November 4: Steve's page will be available in November. Item 99, marketing PCD, IHE to be included with Item 72.Dec. 2, 2009: Steve will post Wiki page, Erin will continue effort. http://wiki.ihe.net/index.php?title=Patient_Care_Device_News. June 23, 2010: Steve posted the Wiki page with links to news. Manny reported that 24x7 gave us visibility in their weekly email newsletter. Aug 4, 2010:Annual webinar was presented by Todd, Steve, and John R., the recording will be available soon. Feb. 2, 2011: Steve reminded us that there is a Wiki page with links to media and members are asked to add to the list. April 13, 2011: Ken suggested a press release for the Survey Monkey results. Manny to send note encouraging companies to post conformance in preparation for a press release. Manny to develop a poster for this purpose. June 22, 2011: Press release: consider issuing one after AAMI, another regarding the commercial availability. July 20, 2011: We had good coverage by 24 x 7. Ken requested that Manny prepare a press release about commercial availability.
78 2011 Stakeholder Survey Development Ray Zambuto Manny August 3, 2011 Open See earlier meetings for history. Ray released updated survey to HIMSS. Steve asked if the results will be available at the October F2F. October 21, 2009: Manny to call Ray this week. November 11, 2009: Ray is attempting to gain HIMSS Analytics support. May 12, 2010, June 23, 2010: Change date.Sept. 29, 2010: Move to Dec. Dec. 1, 2010: Manny to address after the Connectathon. He will check with HIMSS to determine if HIMSS Analytics will support the effort. Feb. 2, 2011: Change date to end of March.April 13, 2011: Christel will survey the Clinical Informatics group she supports. Manny suggested that depending upon results a modified version may be useful in surveying other constituencies. Change date. July 20, 2011: Correct Erin’s line (June 22 re Webex removed from 78, moved to 71). Change name (from 2010 to 2011). Check with Christel for her survey which will later be modified for a wider audience.


Action Items 90-99

No. Action Item Owner Participants Due Open/Closed Description/Update
93 Certification of Systems Claiming Conformance Elliot Deborah Leyva None Available OPEN Elliot and Ioana will approach John Halamka, Steve Lieber and NIST regarding certification for PCD. Greg will follow up with Iaona. Todd emphasized the importance of quick action to assure that PCD is on their radar. Todd will talk to Elliot and Iaona about progress.

Manny to ask Todd what to do with this item. November 11, 2009: Todd has had conversations with Elliot about certification. Among the issues that are out there: What will the role be for CCHIT, how will other national actions affect certification? Elliot is looking at this. Ken mentioned a company that plans to enter into the certification arena. There’s a question about CCHIT’s scope. Todd noted that this is very important from a user’s perspective, and their ability to specify certification in the purchase, and therefore this is very important to vendors. Erin noted that their evaluation of pumps will address components of this issue. May 12, 2010: IHE is discussing; no date available. July 21, 2010: Remove Ioana’s, add Deborah’s name. Deborah noted that the final rule came out yesterday. Ken noted that Meaningful Use for devices is down the road; Deborah said that will occur in 2015. Sept. 1, 2010: John Garguilo noted that NIST is focused on tests for Meaningful Use (MU). Devices will not be the subject of MU until 2014. Sept. 29, 2010: Meaningful Use for devices is likely to begin in 2014. Dec. 1, 2010: Manny to ask Elliot and Debra if they will have time to address this. John Garguilo indicated that when ONC establishes devices within MU the certification companies will likely use NIST Tools. NIST has established a lab certification requirement. He believes that ONC requirements to date have been high level and current PCD efforts are consistent with that approach. Feb. 2, 2011: John Garguilo noted there are now six certification labs. Ken noted that ONC has published a document referring to Stage 2. Manny to distribute Joyce’s email of Feb. 1. Members were encouraged to respond. April 13, 2011: Ken suggested we may need to do something in response to ONC’s work. Paul asked about Continua’s use of NIST test tools; an agreement will be developed. John Garguilo noted that NIST will address the communication wrappers (e.g., WS-*). Paul described work toward computable RTM coding for Continua. June 8, 2011: Paul noted that Continua is satisfied with their process and has placed this on hold for now. John Garguilo reported that the agreement between Continua and NIST will go to the Continua Board shortly. July 20, 2011: Ken asked if PCD can make a contribution to certification for Meaningful Use. John Garguilo suggested that PCD can help lay the groundwork. Greg indicated the VA is working on MU, but is not aware of device elements. The VA does not have a certification process, but is working to have connectivity with VISTA.


Action Items 100-109

No. Action Item Owner Participants Due Open/Closed Description/Update
105 Implementation Guide issues John Garguilo November 30, 2011 OPEN

Initiated F2F May 3, 2010: Erin raised the issue of workflow – e.g., infusion pump messaging takes too long, hospitals complain. Christian observed that clinicians need an indication when data is not reliable for the purpose (e.g., latency, other). John Rhoads indicated that applications need to specify their own behavior. John Garguilo suggested that the implementation guide needs to address these issues. May 26, 2010: John Garguilo will participate, noting this is a broad issue that applies to all domains. Steve noted that this should be addressed by individual profiles and both the PC and TC. Steve asked if a template exists and Todd believes they have this as a Wiki page. This will be a PC item initially. John Garguilo will discuss with others at NIST to gain insight. June 9, 2010: John Garguilo indicated discussions will start soon. Sept. 1, 2010: John Garguilo reminded the PC of the need for this guide and its relation to user and vendor work. He will provide a short presentation at the F2F. Add to Monday F2F agenda. Change date to November 1. Dec. 1, 2010: John Garguilo is looking at other approaches within NIST for potential applicability. Change date to March 2. April 13, 2011: John Garguilo said NIST is looking at this and it will have a section on PCD. It will address issues not found in the TF, but important for developers. Change date to June 1. June 8, 2011: Change date to July 13. July 20, 2011: Change date to August 31: change date to November 30.


107

Clinical System Integration

Todd, Erin -- OPEN

Initiated F2F May 3, 2010: Develop overarching integration of the various profiles and therefore, have core critical-mass functionality that forms a solid foundation; seek integration with other domains. May 26, 2010: Change title to Clinical System Integration. Start with the PC. Todd will take the lead on the Board level. Erin will participate (medication administration). Todd is having a hard time getting Board support. It has implications for IHE’s marketing message. June 9, 2010: Todd indicated that there is a Board meeting tomorrow and this is an agenda item for the following meeting. Add Todd, Erin to the item. July 7, 2010: Remove deadline date. July 21, 2010: Manny to ask Todd if he will continue to lead the item. Aug 4, 2010 Todd continues to drive this item through the Board. Sept. 29, 2010: PCD has approached the new cochair of the ITI TC, Geoffrey Pascoe, to foster collaboration. Dec. 1, 2010: Manny to ask Todd for a suggestion to move this along. Jan. 12, 2011: To be discussed with Todd at the Connectathon. Feb. 2, 2011: Erin offered to take the lead. Steve described this effort as an attempt to provide awareness of how clinical integration requires more than individual profiles. John Rhoads offered that the DCC has formed a subcommittee to look at somewhat the same issue. April 13, 2011: Erin referred to her position on the AAMI Infusion Pump Safety Committee. Clinician’s on the group will define any missing items. Seeking to have this done in 2011. July 20, 2011: Erin reported the AAMI committee is seeking additional participants and one goal is to identify additional work for pump safety. Manny to ask Todd about his interest in this effort.

109 Recruiting Corporate Clinicians -- Anupriyo Chakravarti, Jon Blasingame, Paul Kelley, Steve Merritt, Ken Fuchs, George Bertos, Mike Romig OPEN

Initiated F2F May 3, 2010: Address opportunities to increase clinician involvement; contribute to Use Case development. May 26, 2010: The PC has recruiting items. Make this two items. This will focus on Corporate Clinical Staff - 108 will focus on HIMSS Nursing Informatics. July 7, 2010: Remove deadline date. July 21, 2010: Deborah Leyva, Nuvon, has joined the meetings. Sept. 29, 2010: Jon reported that ACCE is recruiting corporate members and that may help with this. Feb. 2, 2011: Jon will follow up with Christel. June 22, 2011: Recruiting corporate clinicians: Manny to ping Jon. July 27, 2011: Steve suggested that Christel’s survey could help the PC prioritize brief profile proposals.

Action Items 110-119

No. Action Item Owner Participants Due Open/Closed Description/Update
111

Recruit WCM and Other Vendors

Manny, Monroe

Sept. 1, 2011 OPEN

Initiated F2F May 6, 2010: May 26, 2010: Monroe will be talking with Hill-Rom on Tuesday. Manny to recruit vendors needed to support other PCD transactions as well; including ITI-31. June 9, 2010: To date companies have indicated they don’t have resources for this cycle. July 7, 2010: Change date to end of September. July 21, 2010: Manny referred to the Doodle poll, noting that it appears we will be able to have a demonstration at HIMSS11, but it is unlikely we have sufficient support to implement and test WCM at the January Connectathon. Aug 4, 2010: There is enough interest to at least do a New Directions display at HIMSS 2011. Dec. 1, 2010: Change date to March 2. Ken will review the existing poster for use at HIMSS11. Jan. 12, 2011: Manny to ask Steve. Feb. 2, 2011: Manny noted that all four profile proposals were approved for development this year and we will need vendor participation. July 27, 2011: Change date to September 1. Manny will survey the TC about plans for the Connectathon an Showcase.

116

Integration Statements

John Rhoads Greg Staudenmaier and Steve Merritt Oct. 17, 2011 OPEN Opened at Oct. F2F: Define PCD specific additions. April 13, 2011: Add to F2F agenda.June 22, 2011: Integration Statement: Ken described this as an effort to improve the IS. Change date to Fall F2F, add to its agenda. July 27, 2011: Change date to Oct. 17.


Action Items 120-129

No. Action Item Owner Participants Due Open/Closed Description/Update
121 PCD Vision KenFuchs -- October 17, 2011 OPEN Opened during Oct. F2F. Jan. 12, 2011: Change date to March. June 22, 2011: PCD Vision: change date to Oct. F2F.
123 Recruit CMMS Vendors for Event Communication Steve Merritt -- March 15, 2011 OPEN Opened during Oct. F2F Jan. 12, 2011: Steve emailed: The location tracking work may inspire some additional CMMS vendors (as well as Location vendors) to come onboard. We can close that action item for now as it is noted as an open issue for the location tracking work. Jan. 12., 2011: Change date. Ask Steve if he needs help. June 22, 2011: Recruit at AAMI. July 27, 2011: Manny has had some discussions with vendors, will coordinate with Steve. Change date to Sept. 1.


128 Promote RTM Ioana Paul, John Garguilo September 7, 2011 OPEN Spring 2011 F2F: Iona will document the PCD RTM as a "best practice" exemplifying the use of tight structure and rigorous definitions which produce specific coding for each element of the data. PCD with Christel’s assistance will need to find a way to promulgate the message. June 8, 2011: Paul suggested that this include other accomplishments. Paul, John Garguilo will join. Khalil suggested this be directed to IHE domains as well.


Action Items 130-139

No. Action Item Owner Participants Due Open/Closed Description/Update
130 Clinician Recruiting Christel, Steve -- September 7, 2011 OPEN Spring 2011 F2F: Recruiting IT and nursing informatics professionals for participation in PCD:
o Christel encouraged PCD members to submit proposals for presentations at HIMSS12. The HIMSS12 Call for Proposals is open until May 23: http://www.himss.org/ASP/education_annualConf_callProposal.asp June 8, 2011: Ken submitted. Close this portion.
o Christel suggested PCD take advantage of the many HIMSS publications, from formal peer reviewed JHIMSS to informal. June 8, 2011: Steve will lead, starting with MEM. September.
o Christel will conduct a PCD-focused survey: she described her recent survey and her focus on integration into the EMR and preparation for the PCD-focused survey to be distributed soon. June 8, 2011: Christel will conduct the survey. Due July.

July 27, 2011: Change date to Sept. 7.


131 Recruit ACs and Phone Companies Monroe Bob Porterfield, Monroe and Rob August 10, 2011 OPEN Spring 2011 F2F: Bob Porterfield, Monroe and Rob will actively recruit ACs and phone companies. June 8, 2011: Due mid-August, Monroe will lead.
132 OPEN
133 OPEN


134 OPEN
135 OPEN


136 OPEN
137 OPEN
138 OPEN


139 OPEN


Action Items 140-149

No. Action Item Owner Participants Due Open/Closed Description/Update
140 OPEN
141 OPEN
142 OPEN
143 OPEN


144 OPEN
145 OPEN


146 OPEN
147 OPEN
148 OPEN


149 OPEN