Line 56: Line 56:
 
| '''<Owner>:'''  | Juuso
 
| '''<Owner>:'''  | Juuso
 
| '''<Participants>''' | Juuso
 
| '''<Participants>''' | Juuso
| '''<Due Date>'''  | Dec 9, 2015
+
| '''<Due Date>'''  | Dec 16, 2015
 
| '''<Status>''' |OPEN
 
| '''<Status>''' |OPEN
 
| '''<Comments>:'''  | Carried over from AI 78 (AAMI Survey.  Juuso will check with ECRI staff to see if they're willing to do a survey with their customers.  Juuso checke, it looks promising.  Set due date to Oct 28. Moved date out to Nov. 11.
 
| '''<Comments>:'''  | Carried over from AI 78 (AAMI Survey.  Juuso will check with ECRI staff to see if they're willing to do a survey with their customers.  Juuso checke, it looks promising.  Set due date to Oct 28. Moved date out to Nov. 11.

Revision as of 11:20, 9 December 2015

To see changes between current and last(or any earlier) versions of the action item list, click the history tab at the top of the page, select versions to compare and click compare command.

Significant recent changes, other than dates, will be in bold.

Decision meetings will have minutes that require approval. This may be accomplished by email ballot.

See also PCD Planning Committee Closed Action Items page.


Action Items 40 -149

All items have been closed

Action Items 150-159

No. Action Item Owner Participants Due Open/Closed Description/Update
157 Update cookbook to include ACM implementation Monroe Monroe, Darcy Jan 6, 2016 Open Oct. F2F 2012: Not yet in TF FT. PCD-05 still in. Coordination with Pump WG produced change in PCD-05 to R42 from R41. Other elements have been updated as well. Document in the user's guide from the purchaser's perspective. July 10, 2013: Monroe noted that HIMSS published the Interoperability for Dummies Guide and that IHE and PCD needs to promote to purchasing managers. Nov 20, 2013: Need to get info to purchasing staff, Change due date to April 2014 Feb 19, 2014: Presentation at AAMI for purchasing. Change title to Update cookbook to include ACM implementation and move to PC. Note - Moved from TC Feb 19, 2014. June 11, 2014: Move to August meeting.August 27, 2014: Monroe has recruited a volunteer to work on this. He will orient her and get this underway. Change to Sept. Change date to October. Oct 8, 2014: Change date to the F2F meeting. Nov 11, 2014: Volunteer is Darcy Del Dotto, Monroe will invite her to Tues 11/18 3PM ET Co-Chairs call Nov 18, 2014: Monroe will invite Darcy to the Dec 2 Cochair call. Change due date to Dec 2 Dec 10, 2014: No change in status, change due date to Dec 17. Dec 17, 2014: Change due date to January. Jan 14,2015: Working with Darcy on it, will update when we have progress. Change date to February. Update will include MEMDMC and MEMLS, move to March. March 11, 2015: Still working on it, move to April. April 1, 2015: On short hold while Monroe working on CPs, April 28, 2015: Update cookbook to include ACM implementation (Monroe) - Cookbook was drafted, became overlooked when IHE's “Dummies” book was published. The cookbook is still viable, help provide a mechanism for the users/purchasers to effectively choose a system. Darcy reviewed the document. It is very outdated. There is a lot more profiles to be added and she has at least 5 more use cases she would add. She can have document scanned (with notes) and sent. Monroe asked if Darcy would summarize notes and send them to Paul Sh. Change date to May PC. May 20, 2015: No word back from Darcy yet. Change due date to June 24. June 24, 2015: Darcy still in job hunting modse, no new info. Change date to July 8. July 8, 2015: No change, set date to August. Aug 12, 2015: Monroe will have draft ready for F2F, set date to Sep 30 Sept 30, 2015: Monroe will have draft ready for F2F, change to F2F.
Oct 20, 2015: Resource availability limited ability to update so far. Jeff R willing to look at the pump part and Rob will look into the ACM part. Change date to Nov 11. Jeff R has provided Monroe with an updated version of the document for the pump related areas.
Dec 9, 2015: Nothing new change date to next PC meeting.


Action Items 160-169

No. Action Item Owner Participants Due Open/Closed Description/Update


168 Stakeholder Survey Juuso Juuso Dec 16, 2015 OPEN Carried over from AI 78 (AAMI Survey. Juuso will check with ECRI staff to see if they're willing to do a survey with their customers. Juuso checke, it looks promising. Set due date to Oct 28. Moved date out to Nov. 11.
Nov 11, 2015: ECRI can't host survey, but will announce to members. We need a hosting site for the survey. Juuso will check on the announcement deadline. Set date for next PC.
Nov 18, 2015: Juuso updated on deadlines for ECRI to announce. Dec 28 for Jan 1 newsletter, Jan 15 for Jan 18 newsletter.


169 OPEN


Tracking Related Items, 21-40

Number Item and Relationships Date Added to List Date Closed Description/Update
21
22
23
24
25
26
27
28


29


30