Difference between revisions of "IHE Testing and Tools Committee 2009-03-30 Teleconference Minutes"
Jump to navigation
Jump to search
Chrisdcarr (talk | contribs) |
Chrisdcarr (talk | contribs) |
||
Line 24: | Line 24: | ||
::* Delays have made it difficult for NIST to link up its simulation tools | ::* Delays have made it difficult for NIST to link up its simulation tools | ||
:* NIST Plans | :* NIST Plans | ||
+ | ::* NIST likely to get specified funds for Test Tools Development | ||
+ | :::* Designed to be used up over next 2 years | ||
+ | :::* Most of the funding to be contracted out | ||
+ | ::* Increase of 2-3 FTEs internally | ||
+ | ::* Need to develop tools with ability to support NHIN, CCHIT testing (as well as IHE) | ||
+ | ::* Need to coordinate timelines and development plans to avoid redundancy and conflict | ||
:* CCHIT and Cypress | :* CCHIT and Cypress | ||
Revision as of 10:57, 30 March 2009
Attendees
- Lisa Carnahan
- Steve Moore
- Charles Parisot
- Eric Poiseau
- Rob Snelick
- Joan McMillen
- Chris Carr, RSNA
Minutes
1) Tools Development Planning with NIST
-
- January 2010 Connectathon to use Gazelle
- Eric's group (INRIA) to devote focused attention to test engine over the next few months
- Porting 600+ existing tests into test management framework will require time
- Critical task is to refine the test engine first to make population with test scripts possible (need to be defined in BPEL)
- Refactoring of Kudu tests will improve organization and efficiency, but again requires effort
- MIR has two engineer FTEs working on Gazelle (also performs Connectathon management and domain committee work/test plan development)
- INRIA has three FTEs working on Gazelle
- Eric currently applying for renewal of team's funding
- MIR contract renewal with HIMSS/RSNA under discussion: likely equivalent or slightly reduced support
- Plus management oversight by Eric and Steve (one FTE total)
- Delays have made it difficult for NIST to link up its simulation tools
- NIST Plans
- NIST likely to get specified funds for Test Tools Development
- Designed to be used up over next 2 years
- Most of the funding to be contracted out
- Increase of 2-3 FTEs internally
- Need to develop tools with ability to support NHIN, CCHIT testing (as well as IHE)
- Need to coordinate timelines and development plans to avoid redundancy and conflict
- CCHIT and Cypress
2) Connectathon Process Guidelines
- Review updated draft of Connectathon QC guidelines and Sponsor requirements
3) Product Registry Development and Rollout
- Vendor input pilot
- User review pilot
4) Connectathon Monitor/Project Manager Training Event
- Date
- Location
- Cost
- Target Audience